Kakha Kaladze, the mayor of the capital, got acquainted with road rehabilitation works on the one-kilometer section between Tkinvali and Varazi streets in Vake district.
Currently, the grounds for the asphalt cover are being prepared on these streets. Until then the drainage network was repaired and the lower layer of asphalt pavement was completed.
"There has never been a road for years here. We have arranged the drainage system to regulate the water system and now the road pavement works are underway. We have to complete the works by July 10, we launched the project in April, "said Kakha Kaladze.